Pavement and Striping Schedule
Monday, July 11, 2011 – Mill, Patch and Resurface Chervil Court
Vehicles must be off the area by 7:30am on Monday, July 11, 2011 and must remain off the area until 5 pm on Tuesday July 12, 2011 (after the parking space lines and numbers are put down and dry).
Tuesday, July 12, 2011 – Mill and patch work Calypso Drive and Veridan Drive
Vehicles must be off the area by 7:30am and will be able to return by 5pm. Vehicles must be removed from the area by 7am on the day your area is scheduled to be resurfaced. PLEASE see below for your street.
Residents living in 10231 through 10303 Calypso: There is a minimal amount of patching that will be done in this area. However, the parking spaces will be striped and numbered. The full resurfacing of this area will be completed at a later date.
Wednesday, July 13, 2011 – Resurface Calypso Drive (intersection with Veridan Drive to dead end)
Vehicles must be off the area by 7:30am on Wednesday, July 13, 2011 and must remain off the area until 5 pm on Thursday, July 14, 2011 (after the parking space lines and numbers are put down and dry).
Thursday, July 14, 2011 – Resurface Veridan Drive.
Vehicles must be off the area by 7:30am on Thursday, July 14, 2011 and must remain off the area until 5 pm on Friday, July 15, 2011 (after the parking space lines and numbers are put down and dry).
Vehicles not removed from the area will be towed at the owner’s expense.
Tasks will be pushed back to the next day if it rains on the date your area is scheduled. For example: if it rains on Tuesday, July 12, 2011 the work scheduled for Tuesday will be done on Wednesday. Consequently each of the subsequent days scheduled work will be pushed back a day.
Residents may park in the community center parking area during the time the need to be off the area. This is done to protect your property. Vehicles may be parked in the Community Center parking lot on the nights that vehicles must be off the area to allow for the surface to cure and harden. Vehicles will be allowed back on the area as soon as the surface is cured and the parking spaces are painted and dry.